No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
421
15
Pipeline risk assessment
Trans Mountain must file with the NEB,
at least 6 months prior to commencing
construction
, the following information for Line 2 and the new delivery pipelines:
a) the results of the updated risk assessment in a tabular format similar to
that provided in its Line 2 Consequence Report (Filing A3Z8G5). The risk
assessment tables must also include:
i)
any updates to High Consequence Areas;
ii) the risk mitigation method(s);
iii) the mitigated Environmental Risk Scores;
iv) pre-mitigation maximum outflow volumes; and
v) the outflow volumes after mitigation;
b) Environmental Risk Score acceptance criteria, with supporting rationale; and
c) a detailed description of the adequacy of the following from its Line 2 Consequence
Report (Filing A3Z8G5):
i)
the coefficients used in the scoring system equations; and
ii) the values from the scoring tables.
X
16
Quantitative Geohazard Frequency Assessment
Trans Mountain must file with the NEB,
at least 6 months prior to commencing
construction
, an updated Quantitative Geohazard Frequency Assessment for the
new Line 2 and delivery pipeline segments that contains a re-assessment of the
Frequency of Loss of Containment (FLoC) values based on the results of site-specific
field assessments and any required mitigation as determined in the detailed
engineering and design process.
Trans Mountain must provide in the assessment a plan to manage and mitigate
geohazards at any location where the FLoC value is greater than 10
-5
events per year
to reduce the level of risk to as low as reasonably practicable (ALARP), including a
detailed explanation of how the ALARP level has been attained at each location.
X