No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
427
29
Burnaby Mountain tunnel option – rock mass and waste rock management
Trans Mountain must file with the NEB for approval,
at least 6 months prior to
commencing Burnaby Mountain tunnel construction activities
, the following
details on rock mass expected to be encountered during construction of the tunnel
between the Burnaby Terminal and the Westridge Marine Terminal:
a) the characterization of the rock mass quality;
b) waste rock management methods during construction and operations,
if applicable;
c) proposed acid rock mitigation measures, such as the treatment or disposal of
acid rock, if encountered;
d) the locations, sizes, and designs of all confirmed waste rock disposal areas; and
e) plans for disposing any waste rock that is not expected to be stored in the
confirmed waste rock disposal areas.
X
30
Power system protection for pump stations and terminals
Trans Mountain must file with the NEB the following details of its electrical power
system design for each pump station and each of the following: Westridge Marine
Terminal, Burnaby Terminal, Edmonton Terminal, and Sumas Terminal:
a) Descriptions of the overcurrent and ground fault protection schemes including:
i)
a summary of coordination studies between the upstream and downstream
protective devices,
at least 3 months prior to commencing dry commissioning
;
ii) relay settings and time-current curves,
at least 3 months prior to commencing
dry commissioning
;
iii) the specification of neutral grounding resistors,
at least 6 months prior to
commencing construction
;
iv) specifications of contactors, fuses, and circuit breakers,
at least 6 months prior
to commencing construction
; and
v) a description of other electrical protections, relay settings, and trip
characteristics,
at least 3 months prior to commencing dry commissioning
.
b) Consistent with the NEB’s Safety Advisory SA-2015-03, dated 4 May 2015,
at
least 6 months prior to commencing construction
, information confirming
that Trans Mountain has performed the ground fault and arcing fault protection
designs for each pump station and terminal, including:
i)
a means to clear ground faults without intentional time delay if the fault currents
exceed the design limit set by the neutral grounding resistance; and
ii) a means to block the stored energy from other running motors from feeding an
electrical fault in another motor running from the same bus.
This filing must include a description of the ground fault and arcing fault protection
designs including the above measures.
c)
At least 6 months prior to commencing construction
, either:
i)
a written confirmation that Trans Mountain determined during detailed design
that electrical faults will not exceed their design limits and migrate to an arcing
fault; or
ii) for a station or a terminal for which Trans Mountain determined during detailed
design that an electrical fault could exceed its design limit and migrate to an
arcing fault, the electrical configuration of that station or terminal and the
additional equipment and devices that will be used to mitigate the adverse
effects of such arcing faults.
d) Single-line diagrams of the electrical power systems,
at least 6 months prior to
commencing construction
.
X
X
X
X