No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
National Energy Board
428
31
Reactivation of the Niton Pump Station
Trans Mountain must file with the NEB for approval,
at least 6 months prior to
commencing any pump station construction
, an engineering assessment for the
Niton Pump Station, in accordance with CSA Z662. The engineering assessment
must demonstrate that the pump station is fit for its intended service, and meets all
applicable requirements of CSA Z662.
X
32
Sumas Terminal Geotechnical Report
Trans Mountain must file with the NEB,
at least 6 months prior to commencing
construction at the Sumas Terminal
, a geotechnical report that provides feasibility-
level geotechnical design recommendations for the proposed expansion at the
Sumas Terminal.
X
33
Westridge Marine Terminal Onshore Geotechnical Report
Trans Mountain must file with the NEB,
at least 6 months prior to commencing
construction at the Westridge Marine Terminal
, a geotechnical report that
provides feasibility-level geotechnical design recommendations for the proposed
new onshore facilities at the Westridge Marine Terminal, including consideration of
the potential for seismic damage.
X
34
Westridge Marine Terminal Offshore Geotechnical Report
Trans Mountain must file with the NEB,
at least 6 months prior to commencing
construction at the Westridge Marine Terminal
, the final Preliminary Geotechnical
Report on the offshore portion of the Westridge Marine Terminal, based on
the selected pile design option, including consideration of the potential for
seismic damage.