National Energy Board
442
48
Navigation and navigation safety plan
Trans Mountain must file with the NEB, for approval,
at least 4 months prior to
commencing construction
, a Navigation and Navigation Safety Plan that includes:
a) an updated list of navigable waterways to be crossed by or affected by the
Project (including power lines, marine terminal, temporary or permanent bridge
crossings, or other ancillary works that are physically or operationally connected
to the Project);
b) an updated listing of effects of the Project on navigation and navigation safety
for each of the identified waterways identified in a);
c) proposed mitigation measures to address Project effects on navigation and
navigation safety for each of the identified waterways, including adherence to
codes and standards (such as the Canadian Standards Association); and
d) a summary of its consultations with Appropriate Government Authorities,
potentially affected Aboriginal groups and waterway users, regarding their
navigational use of each of the identified waterways. In its summary, Trans
Mountain must:
i) describe the Appropriate Government Authorities, potentially affected
Aboriginal groups, and commercial and recreational waterway users consulted;
ii) describe how Trans Mountain identified those consulted; and
iii) provide a description and justification for how Trans Mountain has incorporated
the results of its consultation, including any recommendations from those
consulted, into the plan.
X
X
X
X
X
49
Technical working group (TWG) reports
Trans Mountain must file with the NEB,
at least 4 months prior to commencing
construction and every 6 months thereafter until after commencing operations
, a
report describing the activities undertaken by the TWGs during the reporting period
and the outcomes of these activities. The reports must include, at a minimum:
a) a list of all members of each TWG;
b) the methods, dates and location of all TWG activities or meetings;
c) a summary of all issues or concerns raised or addressed during the TWG
activities;
d) a description of outcomes or measures that were or will be implemented to
address the issues identified or concerns raised; or, if any measures will not be
implemented, a rationale for why not; and
e) a description of any unresolved issues or concerns, and a description of how
these will be addressed, or a rationale for why no further measures will be
required.
X