No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
443
50
High-voltage alternating current (AC) interference
Trans Mountain must file with the NEB,
at least 4 months prior to commencing
construction
:
a) a report confirming that Trans Mountain has achieved an engineered solution to
mitigate possible damage to pipeline segments caused by the power line fault
current from power line footings and other below ground fault current discharge
facilities of B.C. Hydro’s unshielded transmission power lines that are located
less than 30 metres from those segments. The report must include:
i)
a summary of the above-mentioned engineered solution and an explanation
of how the engineered solution adequately mitigates possible damage to the
pipeline;
ii) a list of pipeline segments where mitigation will be applied; and
iii) an explanation of measures taken by Trans Mountain to reach an agreement
with B.C. Hydro towards implementing the engineered solution.
Trans Mountain must provide a copy of the report to B.C. Hydro at the same time
that it is filed with the NEB;
b) a report detailing how Trans Mountain’s design reduces hazardous induced
voltages on its pipeline segments to meet a maximum 15 VAC under all steady
state operating conditions; and
c) a report demonstrating how Trans Mountain would comply with the
requirements of IEEE Standard 80 to limit touch and step potentials to all points
of contacts to pipeline segments due to power line faults or switching surges,
and include a list of affected
pipeline segments.
X
51
Field changes manual for geohazard mitigation
Trans Mountain must file with the NEB for approval,
at least 4 months prior to
commencing construction
, a field changes manual for geohazard mitigation. This
manual must include:
a) decision criteria for implementing mitigation for any geohazards identified
during construction;
b) specific criteria for implementing changes to the designs, grading, special
materials, protective structures, burial depth, installation procedures, erosion
mitigation measures, and monitoring; and
c) details regarding the required qualifications of the field staff that will implement
the manual.
X