No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
449
60
Environmental and socio-economic assessment - s±58 temporary construction
lands and infrastructure
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing construction
, an environmental and socio-economic assessment for
all temporary construction lands and infrastructure approved pursuant to this Order.
The assessments must include:
a) a list of the locations and dimensions of all temporary construction lands and
infrastructure;
b) environmental alignment sheets or as-built drawings at an appropriate scale,
clearly depicting temporary construction lands and infrastructure;
c) results of any pre-construction surveys within the areas that were not previously
subject to such surveys, and an indication of potential residual effects;
d) all associated mitigation measures that are beyond those identified during the
OH-001-2014 proceeding;
e) analysis supporting the use of the measures in d), including any supplementary
reports;
f) confirmation that Trans Mountain will update the relevant Environmental
Protection Plan(s) to include any relevant information based on any
supplemental surveys completed; and
g) a summary of consultations with Appropriate Government Authorities,
potentially affected Aboriginal groups and affected landowners/tenants, as well
as copies of all written comments that may be provided to Trans Mountain by
those consulted. In its summary, Trans Mountain must provide a description
and justification for how Trans Mountain has incorporated the results of its
consultation, including any recommendations from those consulted, into the
assessment.
X
61
List of temporary infrastructure sites
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction
, a complete list of all temporary infrastructure sites to be constructed for
the Project, and must file any
updates as they become available
. This list must include
information on each site’s location, structures to be installed, the anticipated date for
commencing construction, and activities involved in its construction. The initial list
and any updates must also include the condition numbers (those under the “prior to
commencing construction” phase heading) that are applicable to each site and an
indication of whether each of those conditions has been or remains to be satisfied.
X
62
Construction schedule
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction
, a construction schedule identifying the major construction activities
expected and, on a monthly basis, on the first working day of each calendar month
from the commencement of construction until after commencing operations,
updated detailed construction schedules.
X
X
X
X
X
X
X
X
63
Security Management Programs
Trans Mountain must file confirmation, signed by an officer of the company:
a)
at least 3 months prior to commencing construction
, that it has developed a
Security Management Program for the construction phase of the Project; and
b)
at least 3 months prior to commencing operations
, that it has amended its
operations phase Security Management Program to include operation of the Project;
pursuant to the
National Energy Board Onshore Pipeline Regulations
and CSA Z246.1
(as amended from time to time).
X
X
X
X
X
X
X
X