No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
National Energy Board
450
64
Construction safety manuals
Trans Mountain must file with the NEB:
a)
at least 3 months prior to commencing construction
, the Health and Safety
Management Plan for the Project; and
b)
at least 2 months prior to commencing construction
, Construction Safety
Manuals (Project-Specific Safety Plans) for the applicable Project components.
These must include separate Construction Safety Manuals for pipeline
construction, terminal and pump station construction, Burnaby Mountain tunnel
construction, and Westridge Marine Terminal construction.
These manuals must address routine construction activities, as well as blasting,
tunneling, avalanche safety, safe work in proximity to operational pipelines and
facilities, and special access procedures that may be required in areas subject to
activities other than Project construction.
X
X
X
X
X
X
X
X
65
Hydrology – notable watercourse crossings
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction
, revised flood frequency estimates for all notable watercourse
crossings, as defined by Trans Mountain in its application. These estimates must
incorporate the results of field investigations and bathymetric surveys completed
since the Project application was filed, and be presented in a format similar to
that presented in Application Volume 4A, Appendix I – Route Physiography and
Hydrology Report, Appendix B – Notable Water Crossing Catchment Details
(Filing A56000).
X
66
Risk Management Plan for geohazards
Trans Mountain must develop and file with the NEB,
at least 3 months prior to
commencing construction
, an updated Risk Management Plan for addressing the
threats of existing and potential geohazards during construction of the Project.
This plan must be updated as additional site-specific geotechnical information
is obtained through detailed investigations, and modified as geohazards are
encountered during construction. Trans Mountain must make any updates or
modifications available to the NEB upon request.
X
X
67
Outstanding horizontal directional drilling geotechnical and feasibility reports
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction
, Geotechnical Reports and Horizontal Directional Drilling Feasibility
and Design Reports, along with final design drawings, for each of the following
crossings:
a) Coldwater River 4 crossing;
b) North Thompson River 6 crossing;
c) North Thompson River 7 crossing;
d) Pembina River crossing.
e) Raft River crossing;
f) Sumas River crossing (suitability for Direct Pipe® installation);
g) any additional river crossing along the new Line 2 pipeline segments where
horizontal directional drilling or other trenchless crossing method is being
considered; and
h) the Coquitlam Landfill, if Horizontal Directional Drilling or other trenchless
crossing method is being considered.
X