No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
459
79
Air Emissions Management Plan for the Edmonton, Sumas and Burnaby Terminals
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing construction at each of the Edmonton, Sumas, and Burnaby Terminals,
an
Air Emissions Management Plan for each of those terminals that includes:
a) a description of the baseline, pre-construction conditions informed by relevant
modelling results and recent existing monitoring data;
b) descriptions of the locations of air monitoring sites (on a map or diagram), including
the rationale for the locations selected;
c) the timing for installing air monitoring stations;
d) the methods and schedule for monitoring ambient ground-level concentrations
of potential concern (e.g., volatile organic compounds, ozone, hydrogen sulphide,
mercaptans, criteria air contaminants, secondary ozone and particulate matter, and
reduced visibility) and emissions source tracking;
e) procedures for monitoring station data recording, assessment, and reporting
details, including a description of how the real time and non-continuous air quality
monitoring data will be made available to the public;
f) a description of the public and Aboriginal communication and complaint response
process;
g) the criteria or thresholds that, if triggered or exceeded, will require implementing
additional emissions reduction measures;
h) possible measures that will be implemented as a result of the monitoring data or
ongoing concerns; and
i)
a summary of its consultations with Appropriate Government Authorities,
potentially affected Aboriginal groups and affected landowners/tenants. In its
summary, Trans Mountain must provide a description and justification for how
Trans Mountain has incorporated the results of its consultation, including any
recommendations from those consulted, into the plan.
X
80
Noise Management Plan for construction at terminals and pump stations
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing construction at each terminal and pump station
, a Noise Management
Plan for construction, where residences are within 300 metres of the proposed
construction activities. The plan must include:
a) proposed hours of daytime and nighttime work;
b) noise mitigation measures, including all technologically and economically
feasible mitigation measures;
c) a noise monitoring program, including locations, methodology, and schedule;
d) a description of the public and Aboriginal communication and noise complaint
response process; and
e) a contingency plan that contains proposed mitigation measures for addressing
noise complaints, which may include the temporary relocation of specific
residents.
X
X
X
X