No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
National Energy Board
460
81
Westridge Marine Terminal Environmental Protection Plan
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing construction at the Westridge Marine Terminal
, an updated Project-
specific Westridge Marine Terminal Environmental Protection Plan for the construction at
the Terminal.
The updated Environmental Protection Plan must be a comprehensive compilation
of all environmental protection procedures, mitigation measures, and monitoring
commitments, as set out in Trans Mountain’s Project application, its subsequent filings,
or as otherwise committed to during the OH-001-2014 proceeding. The updated plan
must describe the criteria for implementing all procedures and measures using clear and
unambiguous language that confirms Trans Mountain’s intention to implement all of its
commitments.
The updated Environmental Protection Plan must include the following:
a) environmental procedures (including site-specific plans), criteria for implementing
these procedures, mitigation measures, and monitoring applicable to all Project
phases and activities;
b) policies and procedures for environmental training and the reporting structure for
environmental management during construction, including the qualifications, roles,
responsibilities, and decision-making authority for each job title identified in the
updated Environmental Protection Plan;
c) any additional measures arising from supplemental pre-construction studies and
surveys;
d) updated contingency plans and management plans;
e) updated facility drawings including relevant site-specific resources and mitigations;
f) a description of how Trans Mountain has taken available and applicable Aboriginal
traditional land use and traditional ecological knowledge into consideration in
developing the plan, including demonstration that those Aboriginal persons and
groups that provided Aboriginal traditional land use information and traditional
ecological knowledge, as reported during the OH-001-2014 proceeding and/
or pursuant to Condition 97, had the opportunity to review and comment on the
information; and
g) a summary of its consultations with Appropriate Government authorities and any
potentially affected Aboriginal groups. In its summary, Trans Mountain must provide
a description and justification for how Trans Mountain has incorporated the results
of its consultation, including any recommendations from those consulted, into the
plan.
X
82
Light Emissions Management Plan for the Westridge Marine Terminal
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction at the Westridge Marine Terminal
, a Light Emissions Management
Plan for the Westridge Marine Terminal that includes:
a) a summary of the results of an area lighting study, including how potential
impacts on surrounding communities and safety and operational requirements
were considered;
b) a description of the mitigation and best practice measures considered for
the terminal lighting design and how the proposed design and operation will
minimize the impacts from light on land-based residents and marine users;
c) a summary of its consultations with Port Metro Vancouver, as well as copies
of all written comments that may be provided to Trans Mountain by Port
Metro Vancouver. In its summary, Trans Mountain must provide a description
and justification for how Trans Mountain has incorporated the results of its
consultation, including any recommendations from Port Metro Vancouver, into
the Plan; and
d) a plan for how Trans Mountain will communicate its proposed terminal lighting
design and associated mitigation measures to limit any nuisance lighting
disturbances to land-based residents and marine users.
X