Westridge Marine Terminal (offshore) – pile design
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction at the Westridge Marine Terminal
, the final design basis for the
offshore pile foundation layout of the Westridge Marine Terminal.
X
84
Emergency release system at the Westridge Marine Terminal
Trans Mountain must file with the NEB,
at least 3 months prior to commencing
construction at the Westridge Marine Terminal
, its conclusions on the necessity
of an emergency release system for the loading arms at the Westridge Marine
Terminal. The conclusions must be supported by a comprehensive study describing
the advantages and disadvantages of incorporating an emergency release system.
This study must:
a) consider the application of
i)
emergency release couplers; and
ii) an emergency release system, during both normal operating conditions and
under abnormal conditions such as seismic events; and
b) include a description of the final emergency release system design, if applicable.
X
85
Air Emissions Management Plan – Burnaby Mountain tunnel construction
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing Burnaby Mountain tunnel construction activities
, an Air Emissions
Management Plan for tunnel construction. The plan must include:
a) proposed hours for daytime and nighttime work;
b) sources that would generate air emissions;
c) an Air Emissions and Dust Emissions Management Plan that includes mitigation
measures, their predicted effectiveness, and implementation timeframes; and
d) a description of Trans Mountain’s program for addressing complaints received
during tunnel construction with respect to air and dust emissions, including a
communication and notification plan.
X