No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
National Energy Board
462
86
Burnaby Mountain Tunnel Construction Noise Management Plan
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing Burnaby Mountain tunnel construction activities
, a Burnaby Mountain
Tunnel Construction Noise Management Plan that includes:
a) proposed hours of daytime and nighttime work;
b) baseline daytime and nighttime ambient sound levels at noise sensitive areas
within 500 metres of the entry and exit sites for the tunnel;
c) predicted noise levels at the most affected receptors caused by tunnel
construction without mitigation measures implemented;
d) proposed noise mitigation measures, including all technologically and
economically feasible mitigation measures;
e) predicted noise levels at the most affected receptors with mitigation measures
implemented, including noise contour map(s) showing the potentially affected
receptors;
f) a tunnel construction noise monitoring program, including locations,
methodology, and schedule;
g) criteria that will be used to determine when tunnel construction would be shut
down due to noise;
h) a summary of its consultations with Appropriate Government Authorities
and any potentially affected receptors (residences and businesses), as well
as copies of all written comments that may be provided to Trans Mountain by
those consulted. In its summary, Trans Mountain must provide a description
and justification for how Trans Mountain has incorporated the results of its
consultation, including any recommendations from those consulted, into the
Plan;
i) a description of the public and Aboriginal communication and noise complaint
response processes; and
j) a contingency plan that contains proposed mitigation measures for
addressing noise complaints, which may include the temporary relocation of
specific residents.
X
87
Groundwater Seepage Management Plan – Burnaby Mountain tunnel construction
Trans Mountain must file with the NEB for approval,
at least 3 months prior to
commencing Burnaby Mountain tunnel construction activities
, a Groundwater
Seepage Management Plan for tunnel construction. The plan must include:
a) an estimate quantifying the anticipated average and maximum amounts of
groundwater seepage into the tunnel, and an assessment of any potential
impacts on the water table;
b) a discussion of Trans Mountain’s proposed pumping, treatment, and disposal
options;
c) a description of the potential effects of dewatering of bedrock aquifers,
springs and streams on local groundwater and surface water resources, and of
measures that Trans Mountain would implement to mitigate such effects;
and
d) a description of measures that Trans Mountain would implement during the
operations phase in the event that there is groundwater seepage into the tunnel.
X
88
Project organizational structure for Project construction
Trans Mountain must file with the NEB,
at least 2 months prior to commencing
construction
, a diagram of the Project’s organizational structure (i.e., project
management, design, and field staff) that clearly identifies roles, accountabilities,
responsibilities, and reporting relationships for construction of the applicable Project
components.
X