No.
Conditions with initial filings due prior to commencing construction, or prior to
commencing construction of specified Project component(s)
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
National Energy Board
466
97
Traditional Land Use (TLU) and Traditional Marine Resource Use (TMRU)
Investigation Report
Trans Mountain must file with the NEB for approval,
at least 2 months prior to
commencing construction
, a report describing pre-construction TLU and TMRU
investigations that were not reported during the OH-001-2014 proceeding and that relate
specifically to the Project (up to and including the foreshore lands and boundaries of the
water lease for the Westridge Marine Terminal). The report must include:
a) the name of the potentially affected Aboriginal group to which each investigation
pertains;
b) a description of any identified potentially affected TLU or TMRU sites, resources,
or activities;
c) the methods used to identify the potentially affected TLU or TMRU sites, resources
or activities;
d) a summary of any mitigation measures that Trans Mountain will implement to
reduce or eliminate (to the extent possible) Project effects on TLU or TMRU sites,
resources or activities;
e) confirmation that Trans Mountain will update the relevant Environmental
Protection Plan(s) to include mitigation measures (summarized in (d)) to reduce or
eliminate (to the extent possible) Project effects on TLU or TMRU sites, resources
or activities;
f) a summary of consultations undertaken with or concerns raised by potentially
affected Aboriginal groups regarding investigations on Project effects on the current
use of lands and resources or marine resource use for traditional purposes, as
well as copies of all written comments provided to Trans Mountain by potentially
affected Aboriginal groups to which each investigation pertains. In its summary,
Trans Mountain must provide a description and justification for how Trans Mountain
has incorporated the results of its consultation, including any recommendations
from those Aboriginal groups to which each investigation pertains, into the report;
g) a description of any outstanding concerns raised regarding potential Project effects
on the current use of lands and resources or marine resource use for traditional
purposes, including a description of how Trans Mountain will or address or respond
to them, or an explanation why it will not address or respond to them; and
h) a summary of any outstanding TLU or TMRU investigations or follow-up activities
that will not be completed prior to commencing construction, including estimated
completion date(s), if applicable, and a description of how Trans Mountain has
already identified, or will identify, any potentially affected TLU and TMRU sites,
resources or activities for these outstanding investigations.
Trans Mountain must provide a copy of the report to each potentially affected group
identified in a) at the same time that it is filed with the NEB.
X