No.
Conditions with initial filings due during construction / prior to
commencing operations
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
469
106
Construction progress reports
Trans Mountain must file with the NEB
monthly construction progress reports from
commencing construction until after commencing operations
. The reports must
include information on the progress of activities carried out during the reporting
period, including:
a) safety, environmental and security issues or non-compliances that occurred
during the reporting period;
b) measures undertaken to resolve safety and environmental issues or non-
compliances identified in a);
c) confirmation that security issues identified in a) have been addressed;
d) a description and the location of any change made to geohazard mitigation
measures pursuant to Condition 51; and
e) the location of any pressure tests carried out during the reporting period and a
description of any unsuccessful pressure tests, including the reasons for the lack
of
success of each.
X
X
X
X
X
X
X
X
107
Aboriginal, local, and regional employment and business opportunity
monitoring reports
a) Trans Mountain must file with the NEB,
within 3 months after commencing
construction, and every 6 months thereafter until after commencing
operations
, monitoring reports for Aboriginal, local, and regional employment
and business opportunities for the Project. The reports must include:
i)
a summary of the elements or indicators monitored;
ii) a summary and analysis of Aboriginal, local, and regional employment and
business opportunities during the reporting period; and
iii) a summary of Trans Mountain’s consultation, undertaken during the reporting
period, with relevant Aboriginal groups and local, regional, community and
industry groups or representatives, regarding employment and business
opportunities. This summary must include any issues or concerns raised
regarding employment and business opportunities and how Trans Mountain has
addressed or responded to them.
b) Trans Mountain must file with the NEB,
within 6 months after commencing
operations
, a final report on employment during the construction phase.
X