No.
Conditions with initial filings due during construction / prior to
commencing operations
CPCN
OC2
OC49
Temp
Pump1
Pump2
Tanks
Deact
Trans Mountain Expansion Project 2016
471
110
Authorizations under paragraph 35(2)(b) of the Fisheries Act and Species at Risk
permits – pipeline
For instream activities, except for those related to the Westridge Marine Terminal:
a) for any instream activities that will require Authorization under paragraph 35(2)(b)
of the
Fisheries Act
, Trans Mountain must file with the NEB,
at least 10 days prior to
commencing the respective instream activities
, a copy of the Authorization
under
paragraph 35(2)(b) of the
Fisheries Act
.
b) for any instream activities that will require a permit under the
Species at Risk Act
,
Trans Mountain must file with the NEB,
at least 10 days prior to commencing
the respective instream activities
, a copy of the permit issued under the
Species
at Risk Act
.
c) Trans Mountain must confirm,
within 30 days after commencing operations
, that:
i)
any required
Fisheries Act
Authorizations were obtained from Fisheries and
Oceans Canada and filed with the NEB pursuant to a), or notify the Board if no
Authorizations were required; and
ii) any required
Species at Risk Act
permits were obtained from the competent
minister under the
Species at Risk Act
and filed with the NEB pursuant to b), or
notify the Board if no permits were required.
X
X
111
Joining Programs
Trans Mountain must develop Joining Programs and file them with the NEB
at least
45 days prior to commencing welding of, respectively:
a) field circumferential production, tie-in, and repair pipeline welds, including the
tie-in welds between existing segments and Line 1 or Line 2; and
b) terminals and pump stations.
The Joining Programs must include:
i)
welder qualification requirements;
ii) requirements for welding inspector qualifications and duties;
iii) welding procedure specifications;
iv) non-destructive examination (NDE) specifications;
v) procedure qualification records for welding procedure specifications and NDE
specifications;
vi) a quality assurance program for field welds and welding procedures; and
vii) any additional information that supports the Joining Program.
X
X
X
X
X
112
Pressure testing
a) Trans Mountain must pressure test the new and reactivated pipeline segments,
terminals, and pump stations with a liquid medium.
b) Trans Mountain must file with the NEB,
at least 3 months prior to commencing
pressure testing
, a Pressure Testing Program that demonstrates compliance
with applicable codes, standards, and regulatory requirements.
X
X
X
X
X