Trans Mountain Expansion Project 2016
485
136
Pre-operations full-scale emergency response exercises
a)
Prior to commencing operations
, Trans Mountain must complete a full-scale
exercise for each of the following scenarios:
i)
a 160-cubic-metre diluted bitumen release into Burrard Inlet as a result of a
release from the Westridge Marine Terminal. The exercise must also consider
emergency preparedness and response planning for a release that exceeds a
credible worst case scenario spill event; and
ii) a credible worst-case release volume at the Burnaby Terminal.
b) Trans Mountain must notify the NEB and all potential exercise participants and
observers, including Appropriate Government Authorities, first responders, and
potentially affected Aboriginal groups,
at least 45 days prior to the date of each
exercise in a),
of:
i)
the exercise’s date(s) and location(s);
ii) the exercise’s objectives;
iii) the participants in the exercise; and
iv) the scenario for the exercise.
c) Trans Mountain must file with the NEB and provide to Appropriate Government
Authorities, first responders and potentially affected Aboriginal groups,
within 3
months after completing each exercise in a),
a report on the exercise that includes:
i)
the results of the completed exercise;
ii) areas for improvement;
iii) steps to be taken to correct deficiencies; and
iv) confirmation that an independent third party has evaluated and assessed
the emergency response exercises and that Trans Mountain will consider the
comments generated for future exercises.
X
X
137
Tank roof design for tanks at the Edmonton Terminal
Trans Mountain must install steel pontoon internal floating roofs and fixed roofs with
odour control systems on all of its five proposed tanks at the Edmonton Terminal.
Trans Mountain must file with the NEB,
at least 30 days prior to applying for leave
to open the five proposed tanks
, a letter signed by an officer of the company that
confirms that these roofs were installed.
X
138
Confirmation of firefighting capacity at terminals
Trans Mountain must file with the NEB,
at least 30 days prior to commencing
operations at the terminals
, confirmation that appropriate firefighting capacity, in
accordance with Condition 118, is in place.
X
X